The project schedule and work hours have been changed due to a large boulder that crews encountered during the boring process in mid-November. New work hours will be Monday to Friday from 6 a.m. to 6 p.m. And Sunday to Thursday from 6 p.m. To 6 a.m.
The product team anticipates a new project completion date of February 2010 due to delays in AT&T’s schedule for relocating its equipment
As stated in previous correspondence, the antiquated sewer line running adjacent to Rose Canyon Creek will be replaced by a new pipeline along the west side of Santa Fe Stret from Damon to the bridge at approximately 5181 Santa Fe Street. The replacement pipeline will ensure a cleaner creek bed in the future and eliminate the potential for environmental damage from line ruptures.